Preparing the ground for the new student center. A month later the
footings and walls at the northeast corner are poured. During August,
2000, all the walls have been erected and the lower level floor is prepared
for pouring. Notice the Nancy McGregor House in the background of the
September 1 photo.
|

Nov. 22 |

Jan. 3, 2001 |

Feb. 1 |

Feb. 28
|

March 7 |

March 8 |
The lower level
floor has been poured and the I-beams and steel joists are being prepared
for pouring the main level floor. By February the walls for the rooms
on the main level begin to go up. And toward the end of February, the
Glu-lams (laminated wooden pillars and beams for the Chapel are set in
place.
|

March 16 |

March 21 |

March 21 |

April 3 |

April 4 |

May 2 |
During March
2001, the wooden ceiling in the Chapel is installed, the brick facing
begins, and work on the Bell Tower begins.
During June,
2001, the brick work is finished and the Bell Tower is finished with its
four aluminum crosses.